Sawmill County Park

The original project name was Stone Forest park but the dedicated name was changed to Sawmill County Park.

StoneForestrev copy.jpg (30336 bytes)

Stone Forest Park Estimated Cost Analysis
 Playground $40,000
Tot Lot $20,000
Restrooms $27,000
Group Ramada $20,000
Family Ramadas (3 x $10,000) $30,000
Basketball Court $18,000
Sport Field $30,000
Parking Area (no estimate available)
Fencing $10,000
Contingency $29,250
Total Estimated Cost $224,250